Hardware installed,  finger prints cleaned off glass.    All done!  23 May 2013.   27 part or full days over 5.5 weeks

Hardware installed, finger prints cleaned off glass. All done! 23 May 2013. 27 part or full days over 5.5 weeks

Glass panels in place  21 May 2013

Glass panels in place 21 May 2013

Tiling completed.  20 May 2013

Tiling completed. 20 May 2013

Only half a day available today, but progress nevertheless.  17 May 2013

Only half a day available today, but progress nevertheless. 17 May 2013

First tiles laid, drain channel installed and siliconed in position.  16 May 2013

First tiles laid, drain channel installed and siliconed in position. 16 May 2013

Levels established for tiles,  base tank-tested overnight (no leaks!). Of the 26 tiles to lay, only 7 do not have to be cut - oh joy!  14 May 2013

Levels established for tiles, base tank-tested overnight (no leaks!). Of the 26 tiles to lay, only 7 do not have to be cut - oh joy! 14 May 2013

Joints taped, 2 coats of waterproofing over 2 coats of primer. 11 May 2013

Joints taped, 2 coats of waterproofing over 2 coats of primer. 11 May 2013

After a bit more floor levelling yesterday, the shower base is glued in place and weighted down with 130kg of tiles. 9 May 2013

After a bit more floor levelling yesterday, the shower base is glued in place and weighted down with 130kg of tiles. 9 May 2013

Villaboard screwed in place.  7 May 2013

Villaboard screwed in place. 7 May 2013

The plumber has been; we are ready to roll.  6 May 2013.  $400 for a couple of metres of copper and a few plastic bends! (and his time @75/hr)

The plumber has been; we are ready to roll. 6 May 2013. $400 for a couple of metres of copper and a few plastic bends! (and his time @75/hr)